3. Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. (10 points)

Activity

Normal

Duration (hours)

Normal

Cost ($)

Crash

Duration (hours)

Crash

Cost (S)

Immediate

Predecessors

Crash $ per hour

How Many Hours

Slack

A

2

$10

2

$10

None

B

6

$15

5

$23

A

C

5

$25

4

$31

A

D

3

$20

1

$24

B, C

E

4

$30

2

$40

B, C

F

7

$5

5

$15

B

G

7

$35

6

$45

D, E

H

10

$50

7

$77

F, G

  1. Draw the network diagram. (3 points)
  2. Given the project table above calculate the crash cost for 7 hours of time-savings. (3 points)
  3. Calculate the maximum time-savings available on a $25 crash budget and give the crash sequence (2 points)
  4. Calculate the cost to crash four hours of savings and give the crash sequence. (2 points)

READ BEFORE ANSWERING: DO NOT COPY AND PASTE THE QUESTION FROM THE SAME PROBLEM WITH DIFFERENT NUMBERS, YOU WILL BE DISLIKED.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!