Question: READ BEFORE ANSWERING: DO NOT COPY AND PASTE THE QUESTION FROM THE SAME PROBLEM WITH DIFFERENT NUMBERS, YOU WILL BE DISLIKED. 3. Pirmin's Bike Shop
READ BEFORE ANSWERING: DO NOT COPY AND PASTE THE QUESTION FROM THE SAME PROBLEM WITH DIFFERENT NUMBERS, YOU WILL BE DISLIKED.
3. Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. (10 points)
| Activity | Normal Duration (hours) | Normal Cost ($) | Crash Duration (hours) | Crash Cost (S) | Immediate Predecessors | Crash $ per hour | How Many Hours | Slack |
| A | 2 | $10 | 2 | $10 | None | |||
| B | 6 | $15 | 5 | $23 | A | |||
| C | 5 | $25 | 4 | $31 | A | |||
| D | 3 | $20 | 1 | $24 | B, C | |||
| E | 4 | $30 | 2 | $40 | B, C | |||
| F | 7 | $5 | 5 | $15 | B | |||
| G | 7 | $35 | 6 | $45 | D, E | |||
| H | 10 | $50 | 7 | $77 | F, G |
- Draw the network diagram. (3 points)
- Given the project table above calculate the crash cost for 7 hours of time-savings. (3 points)
- Calculate the maximum time-savings available on a $25 crash budget and give the crash sequence (2 points)
- Calculate the cost to crash four hours of savings and give the crash sequence. (2 points)
READ BEFORE ANSWERING: DO NOT COPY AND PASTE THE QUESTION FROM THE SAME PROBLEM WITH DIFFERENT NUMBERS, YOU WILL BE DISLIKED.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
