Question: Read the article below and answer ALL the questions that follow. MANAGING QUALITY ON CONSTRUCTION SITES IN SOUTH AFRICA: AN EASTERN CAPE CASE STUDY In
Read the article below and answer ALL the questions that follow.
MANAGING QUALITY ON CONSTRUCTION SITES IN SOUTH AFRICA: AN EASTERN CAPE CASE STUDY
In South Africa, construction projects still experience nonconformance to quality requirements as well as cost
and schedule overruns to the detriment of clients. For project success to be attained, conformance to these
parameters is the minimum expectation in the face of other considerations related to client satisfaction. Thus,
through the use of existing literature, and a field study conducted among site management employees working
for general contractors GCs in the Eastern Cape province of South Africa, the management of quality on
construction sites was examined. The study that was descriptive in nature shows that lack of skilled general workers
and artisans contribute to poor quality control and management processes while defects and rework form the main
reason for project quality deviations on the sampled sites. The quality deviations in turn influence the level of cost
and time overrun experienced on construction projects. The study corroborates the literature reviewed in that there
is an interrelationship between cost, quality, and time in South African construction. For example, when the quality of
work is below the required threshold, it leads to cost and time overruns due to rework that requires extra effort
and expense. The value of this explorative study is that both site management and workers should be handson
in terms of managing quality on project sites as failure to do so could have a domino effect relative to other project
considerations.
The quest for optimum reputation by a general contractor GC in the construction industry demands project
performance considerations that would improve the satisfaction of clients. General contractors GCs gain
reputation through fulfilling the needs of clients and the gain of reputation is the major requirement for a GC to
be more competitive in the sector Ashworth The interdependence between the business and project
aspects of construction management has been argued to be crucial in the quest for improved profitability in the sector
Smallwood The interdependence can be gleaned from various construction management related
researched findings from South Africa. Ncwadi and Dangalazana report that South African construction is faced
with productivity and quality problems. The authors contend that productivity and quality in South Africa has dropped,
while health and safety H&S have only marginal improved. As a result, the industry is continuously experiencing
confrontations with regard to dissatisfaction of clients Ncwadi and Dangalana, This may suggest that
contractors have realized the importance of H&S in the construction industry, and then started to focus on H&S at the
expense of other project considerations such as quality. The lack of quality is recognized through nonconformance
of work to the established requirements that is evident when constructed project does not meet clients needs and
specifications Battikha
Concealed quality related problems such as rework during construction process can be projected to other phases of
the process Ford and Sterman, The quality of work is one of the factors that reduces the incidences of rework and
then, determine clients satisfaction levels. Client dissatisfactions conversely could lead to a drop in the market share
and profit of the construction firm that is responsible for a project through its implications for productivity Rivas
Borcherding, Gonzalez and Alarcon, Quality deviations affect clients and other members of the supply
chain, especially contractors. This means nonconformances affect the contractor because it yields penalties in the
form of rework, which can significantly reduce productivity Rivas et al Furthermore, this demonstrates
that quality time, cost, and productivity are always linked together in construction Battikha According to
Joubert, Cruywargen and Basson who cited Grobbelaar and Ngowi top management in
construction firms, both in South Africa and Botswana do not show enough commitment to quality because of a skewed
focus on profit maximization and construction time reduction. In some cases, it might happen that managements
commitment is not clearly communicated to the workforce of a project in terms of access to the quality policy and goals of
a firm and or workers are not motivated to deliver work that conforms to requirements Joubert et al
This illustrated scenario contradicts the needs of clients nowadays as they require quality more than price, especially in
the public sector. The analogy means that clients do not necessarily look towards minimizing cost at the expense quality.
To deal with this problem, commitment to quality is the main fact
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock