Question: Recall from assignment # 2 that the critical path is activities A - D - E - F - H , limiting the process flow
Recall from assignment # that the critical path is activities ADEFH limiting the process flow time to weeks. If you have answered Q correctly, you would see that the bottleneck resource performs none of these activities. There are two statements below.
Statement A: In a process with parallel activities ie more than one path in a process flow dia gram it is possible for the critical resources that perform the critical activities to be different than the resources that are the process bottleneck. In other words, it is possible for the resources that limit flow time to be different than the resources that limit process capacity.
Statement B: In a process with sequential activities like the Cleveland Clinic ie only one path in a process flow diagram the bottleneck resource that limits process capacity must be among the critical activities.
Which of the two statements is correct A B both, or neither Why? Explain.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock