Question: Recall in the schedule resource load chart the time constrained schedule interval ( ES through LF ) has been shaded. Any resource schedule beyond the
Recall in the schedule resource load chart the time constrained schedule interval ES through LF has been shaded. Any resource schedule beyond the shaded area will delay the project.
Assume you have only three resources and you are using a computer that uses software that schedules projects by the parallel method and following heuristics. Schedule only one period at a time!
Minimum slack
Smallest duration
Lowest identification number
Keep a log of each activity change and update you make each periodeg period etc. Use a format similar to the one on page The log should include any changes or updates in ES and slack times each period, activities scheduled, and activities delayed. Hint: Remember to maintain the technical dependencies of the network. Use the resource load chart to assist you in scheduling see pages
List the order in which you scheduled the activities of the project.
Scheduled resource load chart with ES and slack updates
table
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock