Question: Recall in the schedule resource load chart the time constrained schedule interval ( ES through LF ) has been shaded. Any resource schedule beyond the

Recall in the schedule resource load chart the time constrained schedule interval (ES through LF) has been shaded. Any resource schedule beyond the shaded area will delay the project.
Assume you have only three resources and you are using a computer that uses software that schedules projects by the parallel method and following heuristics. Schedule only one period at a time!
Minimum slack
Smallest duration
Lowest identification number
Keep a log of each activity change and update you make each periode.g., period 0-1,1-2,2-3, etc. (Use a format similar to the one on page 241.) The log should include any changes or updates in ES and slack times each period, activities scheduled, and activities delayed. (Hint: Remember to maintain the technical dependencies of the network.) Use the resource load chart to assist you in scheduling (see pages 260-261).
List the order in which you scheduled the activities of the project.
2,3,1,4,5,6
2,1,3,4,5,6
2,1,3,5,4,6
2,1,3,5,6,4Scheduled resource load chart with ES and slack updates
\table[[1,2,3,0,4,1,,,,,,,,,,,,,,,],[2,1,4,0,4,0,,,,,,,,,,,,,,,],[3,1,5,0,6,1,,,,,,,,,,,,,,,],[4,1,6,4,10,0,,,,,,,,,,,,,,,],[5,2,4,5,10,1,,,,,,,,,,,,,,,],[6,2,3,10,13,0,,,,,,,,,,,,,,,],[8,,,,,,,,,,,,,,,,,,,,],[8,,,,,,,,,,,,,,,,,,,,]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!