Question: Recording Long - term Construction: Recognize Revenue at a Point in Time Mullen Construction contracted to build a municipal warehouse for the city of Dallas

Recording Long-term Construction: Recognize Revenue at a Point in Time
Mullen Construction contracted to build a municipal warehouse for the city of Dallas for $840,000. The contract specied that the city would pay Mullen each month the progress billings, less 10%, which was to be held as a retention reserve. At the end of construction, the nal payment would include the reserve. Each billing, less the 10% reserve, must be paid within 10 days after submission of a billing to the city. Transactions relating to the contract follow.
Year 1Construction costs incurred during the year, $224,000; estimated costs to complete, $448,000; progress billing, $212,800; and collections per the contract.
Year 2Construction costs incurred during the year, $392,000; estimated costs to complete, $128,800; progress billings, $313,600; and collections per the contract, assuming revenue from the contract is appropriately recognized over time.
Year 3Construction costs incurred during the year, $112,000. The remaining billings were submitted by October 1, and nal collections were completed on November 30.
Required
a. Provide the Year 1, Year 2, and Year 3 journal entries for (1) construction costs incurred, (2) progress billings, (3) cash collections, (4) revenues and expenses, and (5) to close out accounts upon completion of the contract, assuming revenue from the contract is appropriately recognized at a point in time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!