Question: Recreation facilities selection to maximize daily usage by residents. Resource constraints: 200,000 TL budget; 40 000 m2 of land. Selection constraint: either athletic field or
Recreation facilities selection to maximize daily usage by residents.
Resource constraints: 200,000 TL budget; 40 000 m2 of land.
Selection constraint: either athletic field or gymnasium (not both).
Loading
Recall: Recreation Project
Integer Programming Model:
Maximize Z = 300x1 + 90x2 + 400x3 + 150x4
subject to:
70,000x1 + 20,000x2 + 50,000x3 + 110,000x4 200,000 TL
10x1 + 8x2 + 28x3 + 12x4 40 (thousand m2)
x3 + x4 1 facility
x1, x2, x3, x4 = 0 or 1
x1 = whether to construct a swimming pool or not
x2 = whether to construct a tennis center or not
x3 = whether to construct an athletic field or not
x4 = whether to construct a gymnasium or n
Use excel solver to solve this equation
14:48 29 November Mon %75 % Recall: 0-1 integer model example Recreation facilities selection to maximize daily usage by residents. Resource constraints: 200,000 TL budget; 40 000 m2 of land. Selection constraint: either athletic field or gymnasium (not both). Expected Usage (people/day) Cost (TL) Land Requirement (thousand m2) Recreation Facility Swimming pool Tennis Center Athletic field Gymnasium 300 90 400 150 70,000 20,000 50,000 110,000 10 8 28 12
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts