Reduce Setup Time
Vernon Inc. has analyzed the setup time on its computercontrolled lathe. The setup requires changing the type of fixture that holds a part. The average setup time has been minutes, consisting of the following steps:
Turn off machine and remove fixture from lathe
Go to tool room with fixture
Record replacement of fixture to tool room
Return to lathe
Clean lathe
Return to tool room
Record withdrawal of new fixture from tool room
Return to lathe
Install new fixture and turn on machine
Total setup time
minutes
minutes
a A company plans to setup a machine to increase the productivity. The average setup time is minutes. Do you think the management needs to minimize the setup time. Identify the reason that supports the answer.
a Yes
b No
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock