Question: Reducing overall completion time for an activity by adding more resources in the critical path is called crashing trashing poka - yoke bashing

Reducing overall completion time for an activity by adding more resources in the critical path is called
crashing
trashing
poka-yoke
bashing
 Reducing overall completion time for an activity by adding more resources