Question: Reducing probability to 0% or almost 0% is using which of the following types of risk response plans: a) Transfer Ob) Exploit Oc) Share d)

Reducing probability to 0% or almost 0% is using
Reducing probability to 0% or almost 0% is using which of the following types of risk response plans: a) Transfer Ob) Exploit Oc) Share d) Avoid