Question: Refer to case 6 . 2 - Ventura Baseball Stadium - part A from Page 2 0 9 of the textbook Answer all three questions
Refer to case Ventura Baseball Stadium part A from Page of the textbook
Answer all three questions given under the assignment section within case in a word
file
Submit the Microsoft project file copy as a part of your response see class examples
NOTE
The Microsoft project file should show the following
Gantt chart
Project network diagram
Critical path highlighted in the Gantt chart and network diagram
Ventura Baseball StadiumPart A
The G&E Company is preparing a bid to build the new seat Shoreline baseball stadium. The construction must start on June
and be completed in time for the start of the season. A penalty clause of $ per day of delay beyond April rd is written
into the contract.
Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as
much as $ million on the project. He also said that if they were successful, the prospects of future projects would be bright, since there is
a projected renaissance in building classic ballparks with modern luxury boxes.
ASSIGNMENT
Given the information provided in Table construct a network schedule for the stadium project and answer the following questions:
Can the project be completed by the April rd deadline? How long will it take?
What is the critical path for the project?
Based on the schedule, would you recommend that G&E pursue this contact? Why? Include a onepage Gantt chart for the stadium
schedule. TABLE Ventura Baseball Stadium Case
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock