Question: Refer to the activity network table above ( in problem 3 ) and using MS Project software. Suppose that we modified the original table slightly

Refer to the activity network table above (in problem 3) and using MS Project software.
Suppose that we modified the original table slightly to show the following predecessor
relationships between tasks and resources assigned to perform these activities. Enter this
information using MS Project in order to produce a Gantt chart. Assume that each resource has
been assigned to the project activity on a full-time basis.
Activity Duration Predecessors Resource Assigned
A. User survey 4 None Gail Wilkins
B. Coding 12 A Tom Hodges
C. Debug 5 A Tom Hodges
D. Design interface 6 B, C Sue Ryan
E. Develop training 5 D Reed Taylor
a) Using the Resource Usage view, can you determine any warning signs that some
member of the project team has been over-assigned to the project team?
b) Click on the Task Usage view to determine the specific days when there is a conflict in
the resource assignment schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!