Question: Refer to the attached 2 tables below - one is actual costs and one is budgeted costs to answer the below questions: ( Amounts are

Refer to the attached 2 tables below - one is actual costs and one is budgeted costs to answer the below questions:
(Amounts are in thousands of dollars).
a) What is the TBC for the entire 10-week project? (2 marks) Use Fig.5.6 to answer this question.
b) What is the cumulative budgeted cost at end of week 6?(2 marks) Use Fig.5.6 to answer this question.
c) What is the cumulative actual cost at the end of week 6?(2 marks) Use Fig 5.7 to answer this question.
d) Determine whether there is a cost overrun or underrun and how much? (4 marks) Use both figures to answer this question.
e) What is causing it?(here you need to look at Tasks 1,2 and 3 and compare to the budget for each task to determine what is driving the change vs budget)(4 marks) Use both figures to answer this question.
 Refer to the attached 2 tables below - one is actual

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!