Question: Refer to the tasks outlined below. Using MS Project, develop a Gantt chart for the tasks and show the critical path. Note the hierarchical structure
Refer to the tasks outlined below. Using MS Project, develop a Gantt chart for the tasks and show the critical path. Note the hierarchical structure of the tasks. Blue represents the top level. Please note that some tasks and dependencies were omitted/changed from the original version, and the task durations were shortened so the chart fits on a single page. Normally, these would take much longer. Hint: Copy and paste the task and duration columns.

Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
