Question: Referring to Appendix 3, in what weeks should planned orders be released for item A assuming no safety stock? Select one: O a. 1, 3,

Referring to Appendix 3, in what weeks should
Referring to Appendix 3, in what weeks should
Referring to Appendix 3, in what weeks should planned orders be released for item A assuming no safety stock? Select one: O a. 1, 3, and 4 O b. 1, 2, 4, and 5 O c. 1, 2, 3, 4, and 5. O d. 2, 4, and 5 Period 3 1 2 4 5 6 Gross Requirements 50 50 50 50 50 50 Scheduled Receipts On Hand Inventory 75 Planned Order Relaeses Item A, Lead Time = 1 Week, Order Quantity = 75