Question: Referring to the table, draw the WC 2 loading using Johnson's Rule (10 pts) Jobs Work Center 1 Work Center 2 Due Dates (in
Referring to the table, draw the WC 2 loading using Johnson's Rule (10 pts) Jobs Work Center 1 Work Center 2 Due Dates (in Days) (in Days) 4 3 2 5 4 4 N 3 114 st 10 5 1 6 2 5 15 16 8 5 10