Question: -Referring to the table, if you are using the earliest due date, is completion time in WC 1? Jobs Work Center 1 ( in Days

-Referring to the table, if you are using the earliest due date, is completion time in WC 1?

Jobs

Work Center 1

( in Days )

Work Center 2

( in Days )

Due Dates

1

7

3

20

2

10

2

12

3

6

4

10

4

6

8

15

5

1

5

18

a.

19 days

b.

30 days

c.

27 days

d.

26 days