Question: Regarding activity resources estimation, what does expert judgment imply? Group of answer choices Using mathematical models to predict resource needs Following guidelines from the PMBOK

Regarding activity resources estimation, what does "expert judgment" imply? Group of answer choices Using mathematical models to predict resource needs Following guidelines from the PMBOK Consulting with individuals experienced in similar projects Using software to estimate resources