Question: Relevant information for a project consisting of activities A , B , dots, H is provided in the table below and the project network is
Relevant information for a project consisting of activities dots, is provided in the table below and the project network is provided.
tableActivityTime in WeeksCost,tableImmediatePredessorsNormalCrash,Normal,Crash,A$$NAB$$AC$$AD$$B CE$$B CF$$DG$$EH$$F G
When all activities are completed in normal time, what is the project completion time?
To reduce project completion time by week at minimum cost, which activity, or activities should be crashed? Enter the letter for the activity or egBAH
What is the incremental cost to reduce project completion time by week at minimum cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
