Question: Reliable Part Co . Has signed a contract with a farm - equipment manufacturer for 1 0 0 , 0 0 0 parts to be

Reliable Part Co. Has signed a contract with a farm- equipment manufacturer for 100,000 parts to be delivered
uniformly over one year. Each part is going to be processed sequentially in three departments (pressing, drilling,
and grinding) with the following production data. Assume that company operates 250 days per year.
Departments
Pressing Drilling Grinding
Working time available / day 8 hours 8 hours 8 hours
Processing time / part 4 min 12 min 8 min
Average down time / day 40 min 80 min 60 min
Average non-productive / day 15 min 30 min 20 min
Percentage of defectives 3%9%5%
(a)[5 pts] Determine the working minutes per day, reliability of machines, and actual performance efficiency
for each department.
(b)[5 pts] Determine the required daily production input for each department if all defectives are discarded as
scrap.
(c)[5 pts] Determine the machine fractions required for each department.
(d)[5 pts] The effect on equipment requirement if the company were to go on two shift (2x8 hrs/day)?
(e)[5 pts] As a result of a recent preventure-maintenance program the average down time in each department
was reduced by 50%. Determine the effect on equipment requirement

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!