Question: Remaining Time: 1 hour, 54 minutes, 52 seconds. Question Completion Status: QUESTION 3 Charismas trees cost $25 and sell for $80, and at the end
Remaining Time: 1 hour, 54 minutes, 52 seconds. Question Completion Status: QUESTION 3 Charismas trees cost $25 and sell for $80, and at the end of the season not only they have no salvage value, but it also costs $5 to dispose of each of them How many trees should the local shop manager order for the next season, know that the demand for the trees is normally distributed with a mean of 250 and a standard deviation of 252 Link to Formulas. Z-Table & Excel Worksheet) 120 105 275 85% 160 QUESTION 4 Which of the following smoothing constants would make an exponential smoothing forecast equivalent to a naive forecast? (Link to Fornutos. Z Table & Excel Worksheet) 0 05 10 1 divided by the number of periods Click Save and Submitowahi nubuit.chel Save all Remaining Time: 1 hour, 54 minutes, 30 seconds. Question Completion Status: and through the entire supply pipeline QUESTION 5 According to our lectures, Supply Chain Management is "the art and science of integrating the flow of from the Suppliers' Suppliers to Customers' Customers Raw material Supplies, Finances, and Information Raw material Supplies, Products, and Finances Supplies Products, Returns, and Finances Materials. Products, Finances and Information Materials, Products, Returns, and Finances QUESTIONS A forecast based on the previous forecast plus a percentage of the previous forecast ervor is A naive forecast A simple moving average forecast A centered moving average forecast An exponentially smoothed forecast An associative forecast QUESTION An activity on a PERT network as these time estimates optimistic - mostly and permis- Wherepected Link to Formulas Table Excel Worksheet 500 board XCOM Remaining Time: 1 hour, 54 minutes, 24 seconds. Question Completion Status: QUESTION 7 An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 9. What is its expected activity time? (Link to Formulas. Z-Table & Excel Worksheet) 5.00 5.33 5.67 10.67 32.00 QUESTIONS Under lot-for-lo, order stres for component parts are essentially determined directly from which one of the following Gross requirements Net requirements Economic order quantity Gross requirements not requirements Net requirements - amount on-hand QUESTION The following data sets a sample of the daily demand and the stock replenishment ad fime of products level of 96 what is the appropriate reorder point for this produ