Question: Remaining Time: 32 min 53 seconde Question Completion Status: Moving to another question will save this response Question 13 A project has the following activities,

Remaining Time: 32 min 53 seconde Question
Remaining Time: 32 min 53 seconde Question Completion Status: Moving to another question will save this response Question 13 A project has the following activities, immediate predecessors and activities duration in woeka. IMMEDIATE PREDECESSOR(S) ACTIVITY A TIME (DAYS) 2 5 B 1 10 B D 3 AD E 6 F 8 EF G a) The critical path of the project is weeks b) The total project completion time is Moving to another question will save this response