Question: RENDU ELU PLEASE SHOW ALL YOUR WORK AND EXPLAIN YOUR ANSWERS. Based on the activity time estimates, the expected times for each of the activities
RENDU ELU PLEASE SHOW ALL YOUR WORK AND EXPLAIN YOUR ANSWERS.
Based on the activity time estimates, the expected times for each of the activities are :

Problem 3.13 (similar to) Question Help O A renovation of a Hard Rock Cafe gift shop has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed. a m b Activity A 11 26 18 - 15 30 18 14 18 19 20 41 18 19 20 21 9 17 17