Question: rent knowledge areas 2 New process names Question 3 [20] You are the project manager of StarGate Inc., a company that specialises in the
![rent knowledge areas 2 New process names Question 3 [20] You are](https://s3.amazonaws.com/si.experts.images/answers/2024/05/6655f2e7d51a5_7756655f2e7d0171.jpg)
rent knowledge areas 2 New process names Question 3 [20] You are the project manager of StarGate Inc., a company that specialises in the design and distribution of these covers for a major cell phone manufacturing company in the Westerr production of durable cell phone covers. Your current project involves the manufacturing and Cape. The following information is available: The client pays four separate monthly payments of R150 000 one month af invoice. You employ labour at R90 000 per month paid in the month of work. You buy materials at R30 000 per month; the supplier gives one month's credit.