Question: Report an Error What is the difference between a budget and a cost baseline? question 5 of 5 O A cost baseline is time phased
Report an Error What is the difference between a budget and a cost baseline? question 5 of 5 O A cost baseline is time phased to indicate when in O A cost baseline doesn't include costs for materials. the project lifecycle money will be spent. O A budget includes all the costs for the project. O A cost baseline includes all the costs for the project