Question: REQUIRED: a . What run quantity ( EPQ ) should be used to minimize total annual costs? b What is the length of a production

REQUIRED:
a. What run quantity (EPQ) should be used to minimize total annual costs?
b What is the length of a production run in days?
c. What is the cycle time?
d What would the average inventory be for this lot size?
e About how many runs per year would there be?
f
If the manager wants to run another job between runs of this item, and needs a minimum
of 10 days
per cycle for the other work, will there be enough time? Note: Cycle time - Run time -
Setup time must be greater than or equal to 10!
g
During production, at what rate will inventory build up? Note: Buildup rate is p-u!
 REQUIRED: a. What run quantity (EPQ) should be used to minimize

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!