Question: Required: Calculate variable cost per unit using the high-low method. Calculate fixed costs. Calculate estimated costs at 2,700 maintenance hours. Problem 3 Maintenance Hours Maintenance
Required:
- Calculate variable cost per unit using the high-low method.
- Calculate fixed costs.
- Calculate estimated costs at 2,700 maintenance hours.
| Problem 3 |
|
|
|
| Maintenance Hours | Maintenance Cost (SAR) |
| January | 2,500 | 32,500 |
| February | 1,800 | 29,000 |
| March | 2,800 | 32,000 |
| April | 1,200 | 16,000 |
| May | 1,600 | 22,500 |
| June | 2,200 | 27,000 |