Question: Required information Problem 6 - 1 0 ( Algo ) Long - term contract; revenue recognition over time [ LO 6 - 8 , 6

Required information
Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
Skip to question
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400
Estimated costs to complete as of year-end 5,609,0002,054,0000
Billings during the year 2,110,0003,736,0004,154,000
Cash collections during the year 1,855,0003,500,0004,645,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 2
2-a. In the journal below, complete the necessary journal entries for the year 2024(credit Cash, Materials, etc. for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025(credit Cash, Materials, etc. for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2026(credit Cash, Materials, etc. for construction costs incurred). Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
Skip to question
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400
Estimated costs to complete as of year-end 5,609,0002,054,0000
Billings during the year 2,110,0003,736,0004,154,000
Cash collections during the year 1,855,0003,500,0004,645,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 2
2-a. In the journal below, complete the necessary journal entries for the year 2024(credit Cash, Materials, etc. for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025(credit Cash, Materials, etc. for construction costs incurred).
2-c. In the journal below, complete the necessary journal entrie Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
Skip to question
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400
Estimated costs to complete as of year-end 5,609,0002,054,0000
Billings during the year 2,110,0003,736,0004,154,000
Cash collections during the year 1,855,0003,500,0004,645,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 2
2-a. In the journal below, complete the necessary journal entries for the year 2024(credit Cash, Materials, etc. for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025(credit Cash, Materials, etc. for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2026(credit Cash, Materials, etc. for construction costs incurred). Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
Skip to question
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400
Estimated costs to complete as of year-end 5,609,0002,054,0000
Billings during the year 2,110,0003,736,0004,154,000
Cash collections during the year 1,855,0003,500,0004,645,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 3
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract.Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
Skip to question
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400
Estimated costs to complete as of year-end 5,609,0002,054,0000
Billings duringProblem 6- Can you please include all steps. thanks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!