Question: Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] Skip to question [The following information applies to the questions displayed below.]

Required information

Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]

Skip to question

[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600
Estimated costs to complete as of year-end 5,658,000 1,886,000 0
Billings during the year 2,020,000 4,294,000 3,686,000
Cash collections during the year 1,810,000 3,800,000 4,390,000

Westgate recognizes revenue over time according to percentage of completion.

Problem 6-10 (Algo) Part 4

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,542,000 $ 3,810,000 $ 3,210,000
Estimated costs to complete as of year-end 5,658,000 3,110,000 0

2021 2022 2023
Revenue $3,100,000
Gross profit (loss) $558,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!