Question: Required information Use the following information for the Quick Study below. (Algo) [The following information applies to the questions displayed below.) BatCo makes baseball bats.
Required information Use the following information for the Quick Study below. (Algo) [The following information applies to the questions displayed below.) BatCo makes baseball bats. Each bat requires 2.00 pounds of wood at $18 per pound and 0.35 direct labor hour at $30 per hour. Overhead is assigned at the rate of $60 per direct labor hour. QS 21-6 (Algo) Total Cost variances LO P2 Assume the actual cost to manufacture 140 bats is $10,150.00. Compute the total cost variance and identify it as favorable or unfavorable. (Indicate the effect of the variance by selecting favorable, unfavorable, or no variance.) $ 8,515 Actual cost Budgeted standard cost Total cost variance $ 8,515