Question: Requirement: 1. Prepare normal times, normal cost schedule 2. Prepare minimum cost (least cost) crash time schedule 2. Assume that you are a project manager

Requirement: 1. Prepare normal times, normal cost schedule 2. Prepare minimum cost (least cost) crash time schedule
2. Assume that you are a project manager of the project whose activity network and other information are shown below: D 2 6 A G 1 5 7 F H B E 3 3 Cost ($) Activity A B D E F G H I Normal 1 4 7 7 6 5 7 3 4 Crash 9 6 9 12 7 8 18 5 7 Time (day) Normal 9 7 12 10 12 6 7 14 8 Crash 6 2 6 8 8 2 3 4 5 Requirement: 1. Prepare normal times, normal cost schedule 2. Prepare minimum cost (least cost) crash time scheduleStep by Step Solution
There are 3 Steps involved in it