Question: Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3.

Requirements

1.

Complete the performance evaluation report for this subunit.

2.

Based on the data presented, what type of responsibility center is the subunit?

3.

Which items should be investigated if part of the management's decision criteria is to investigate all variances exceeding

$2,700

or 12%?

4.

Should only unfavorable variances be investigated? Explain.

Product Actual Budgeted Variance

(U or F)

Direct materials. $21,480. $20,000

Direct labor 16,660. 17,500

Indirect labor. 28,140. 24,000

Utilities 10,940. 10,000

Depreciation. 21,800 21,800

Repairs 4,195. 5,000

and maintenance

Total $103,215 $98,300

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!