Question: Requirements input for a lot-sizing problem are (75, 120, 80, 75). Setup cost is $250, and holding cost is $1 per unit per period. The

Requirements input for a lot-sizing problem are (75, 120, 80, 75). Setup cost is $250, and holding cost is $1 per unit per period. The capacity each period is 100. Formulate this as a mixed integer programming problem.