Question: Research and submit data sheets for three different materials needed for the term project assigned this term. As a project engineer you are requested to

Research and submit data sheets for three different materials needed for the term project assigned this term.
As a project engineer you are requested to prepare a Procurement Schedule for the critical materials required for the project. Use the following project schedule and minimum times for submittal review and material delivery to fill the procurement schedule.
The contractor needs 1 day to review suppliers/subcontractors submittals
The Contractor needs 1 day to order any material once approved by the architect
The Architect needs 7 days to review each of the electrical rough-in, concrete masonry, plumbing, metal deck, fire sprinkler, drywall, ceramic tiles, and metal window submittals; and 14 days to review each of the paint, fire alarm, toilet accessories, and carpet =
The Suppliers need 3 days to deliver electrical rough-in, paint and carpet; 7 days to deliver concrete masonry. plumbing, fire sprinkler, ceramic tiles, metal window, fire alarm and toilet accessories; and 14 days to deliver metal deck and drywall
All materials should be delivered to the site at least 3 days before first needed
All dates and times should fall on business days
The project sehedule is 60 hours per week (10 hours 6 days including Saturdays)
Project Schedule
\table[[ACTIVITY DESCRIPTION,\table[[DURATION],[(DAYS)]],\table[[EARLY],[START]],\table[[EARLY],[FINISH]]],[Shoring,5,05-May-25,12-May-25],[Rebar: Footings,10,05-May-25,19-May-25],[Concrete,5,05-May-25,12-May-25],[Rebar: Foundation Wall,15,16-May-25,06-Jun-25],[Steel: Embed, Bolts,15,16-May-25,06-Jun-25],[Drywell,5,19-May-25,27-May-25],[Electrical Rough-in,10,21-May-25,04-Jun-25],[Plumbing Rough-in,10,21-May-25,04-Jun-25],[Rebar: Slabs,10,21-May-25,04-Jun-25],[Cure/Seal,5,21-May-25,28-May-25],[Steel: Columns,10,23-May-25,06-Jun-25],[Concrete Masonry,15,27-May-25,17-Jun-25],[Rebar: Tilt-Up Panels,15,28-May-25,18-Jun-25],[Tilt-Up Panel,10,28-May-25,11-Jun-25],[HM Doors,5,02-Jun-25,09-Jun-25],[Plumbing,3,10-Jun-25,13-Jun-25],[HVAC,15,10-Jun-25,01-Jul-25
Research and submit data sheets for three

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!