Question: Research on project management capability maturity models has found that: O 1) Project performance does not improve at higher levels of maturity. O 2) Companies

Research on project management capability maturity models has found that: O 1) Project performance does not improve at higher levels of maturity. O 2) Companies that attain higher levels of project management maturity experience improved schedule and cost performance. 0 3) Companies at lower levels of maturity tended to gain better performanc using project management software tools. 0 4) Project management training led to reduced performance