Question: Resource Leveling Project Data Assigned Priority Rule: EST: Minimum Earliest Start Time First Tiebreaker* rule: Lowest Activity Index (#) First *Hint: Use the tiebreaker if


Resource Leveling Project Data Assigned Priority Rule: EST: Minimum Earliest Start Time First Tiebreaker* rule: Lowest Activity Index (\#) First *Hint: Use the tiebreaker if the assigned priority rule results in a tie among two or more activities. Resource Leveling Questions Question 1: Resource Leveling. Calculations Question 2: What is the total duration of the project if planned with Serial Generation Scheme? Question 3: What is the total duration of the project if planned with Parallel Generation Scheme? 1) Table data are shown below, REF-network diagrar 2) The total duration for project is 33 3) Here, the critical path is the longest path among paths 4) Only one critical path 5) Here, the critical path is BDFI 6) Critical path activities are B, D, F and
Step by Step Solution
There are 3 Steps involved in it