Question: Resource leveling uses a trial - and - error method to test delaying Question 8 options: all activities with a positive slack all non -
Resource leveling uses a trialanderror method to test delaying
Question options:
all activities with a positive slack
all noncritical activities
all critical activities
only noncritical activities with positive slack