Question: Resource Profile planning differs from capacity planning using overall factors (CPOF) and Capacity Bills by considering which of the following? I. Customer orders II. Inventory
Resource Profile planning differs from capacity planning using overall factors (CPOF) and Capacity Bills by considering which of the following?
I. Customer orders II. Inventory plans
Group of answer choices
II only
I only
Neither I nor II
Both I and II