Question: Resource splitting ( interrupting the continuous stream of work on an activity at some midpoint in its development process and applying that resource to another
Resource splitting interrupting the continuous stream of work on an activity at some midpoint in its development process and applying that resource to another activity for some period before returning the resource to complete the original task is not an alternative technique to resource leveling because of the excessive costs associated with splitting the task.
True
False