Question: Respond to the Following Problems Reference pages 6 8 7 - 7 0 1 in the textbook: Data Analysis - Earned Value Analysis You are
Respond to the Following Problems
Reference pages in the textbook: Data Analysis Earned Value Analysis
You are a project manager on a project that uses earned value management. The project has the following budget and status:
Project Duration months:
Current Reporting Period month:
BAC:
$
Cumulative PV:
$
Cumulative AC:
$
of the project completed through the reporting period:
Estimate to Complete:
$
Part :
Based on this information, determine the following:
Cumulative EV
Schedule Variance SV
Schedule Performance Index SPI
Cost Variance CV
Cost Performance Index CPI
EAC bottomup
VAC bottomup
TCPI
Based on your calculations above, respond to the following:
What is the status of project accomplishment performance through the current reporting period? Why?
What is the status of project cost performance through the current reporting period? Why?
Is the project projected to complete overbudget or underbudget? Why?
Interpret the TCPI metric.
Part :
Based on your calculations above, an inexperienced and arrogant project analyst from the project management office has computed an additional metric: Cost Schedule Index, which equals SPI CPI. He wants you to report this metric to the customer, instead of SPI and CPI separately. What should you do and why?
The program manager doubts your numbers. In particular, he does not believe your EAC number and requests that you calculate the EAC not assuming future performance will behave like past performance.
Compute EAC when cost performance is negative and schedule dates must be met: EAC AC BAC EVCPI times SPI
Compute EAC using actual costs to date and assuming ETC uses budgeted rate: EAC AC BAC EV
Interpret the results of the EAC in a
Interpret the results of the EAC in b
Based on these new calculations, what do you think the program manager will request from you regarding the bottomup EAC?
Part :
You are having a hallway conversation with the same project analyst who is now realizing that he may not know as much about earned value management as he thought when he joined the company. Still, he is convinced that the following statements below are correct. How would you respond to him based on each statement ie formulate a specific response and supporting rationale for each statement below
EAC becomes Cumulative AC at project completion.
Cumulative EV can be greater than BAC at project completion.
EAC can be smaller than BAC at project completion.
ETC can be greater than at project completion.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
