Question: Return to comtent Durewtien 9 7 er tee Which statement about a project's critical path is false? If a project is to stay on schedule,
Return to comtent
Durewtien er tee
Which statement about a project's critical path is false?
If a project is to stay on schedule, no activity on the critical path can be late.
The duration of the critical path dictates the length of the project.
The critical path is defined as the path that has the most individual activities on it
To reduce the duration of a project, you must reduce the length of the critical path via crashing.