Question: Return to content Question 6 of 40 Which statement about project deliverables is false? End deliverables and intermediate deliverables should go to the project sponsor.

Return to content Question 6 of 40 Which statement about project deliverables is false? End deliverables and intermediate deliverables should go to the project sponsor. Deliverables should be accomplished in the time frame between status reports. Deliverables can be either tangible or intangible. Deliverables can serve as measures of a project's progress. Previous Next