Question: Return to question Exercise 2-10 Applying Overhead Cost to a Job (LO2-2] Sigma Corporation applies overhead cost to jobs on the basis of direct labor
Return to question Exercise 2-10 Applying Overhead Cost to a Job (LO2-2] Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $6,500 for direct materials, $9,000 for direct labor, and $5,760 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $3,200 for direct materials and $4,100 for direct labor. Required: 1a. Should any overhead cost be applied to Job Wat year-end? Yes O No 1b. How much overhead cost should be applied to Job W? Answer is complete but not entirely correct. Overhead cost $ 8.200