Question: Right Answer and explanation? PB1. LO 4.12 e For each item listed, state whether a job order costing system or process costing system would be
PB1. LO 4.12 e For each item listed, state whether a job order costing system or process costing system would be best. Job Order Costing System:Items that are made to order Process Costing System: Mass-produced items A. television repair - job order costing system B.cell phone charge cords-process costing system C. glassware with company logo - job order costing system D.dog food process costing system E. golf balls process costing system F. hotel signs to welcome guests job order cost system G.highlighters and pens-process costing system