Question: RISK MANAGEMENT CLM 017 You are managing a base realignment program to consolidate four bases, while expanding/modernizing the surviving base. As part of that program,
RISK MANAGEMENT CLM 017
You are managing a base realignment program to consolidate four bases, while expanding/modernizing the surviving base. As part of that program, there is a requirement to reduce water run-off by 25% from both bases. You have heard from a colleague about a new water-permeable concrete that allows water infiltration at a rapid rate and lasts for up to 10 years. Is this a risk or an opportunity?
1. Opportunity
2. Neither risk or opportunity
3.Not Enough Information
4. Risk