Question: risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue.

risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue What should the risk manager do next to find out the correct limit? Find out the stakeholders' risk appetite Perform a sensitivity analysis of the risk Review the agreed-upon risk tolerance Use industry standard risk thresholds

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!