Question: Risks are prioritized based on Group of answer choices the likelihood of occurrence and degree of impact. the order they are identified. he gut feeling

Risks are prioritized based on

Group of answer choices the likelihood of occurrence and degree of impact.

the order they are identified.

he gut feeling of the project team.

the priorities set in a different project.