Question: Risks are prioritized based on Group of answer choices the likelihood of occurrence and degree of impact. the order they are identified. he gut feeling
Risks are prioritized based on
Group of answer choices the likelihood of occurrence and degree of impact.
the order they are identified.
he gut feeling of the project team.
the priorities set in a different project.