Question: Risks on the critical path should be Question 7 1 options: given lower priority than those activities with positive total slack. given equal priority than
Risks on the critical path should be
Question options:
given lower priority than those activities with positive total slack.
given equal priority than those activities with positive total slack.
given higher priority than those activities with positive total slack.
given higher priority than those activities with no total slack.