Question: Roberto is NOT using a Risk Register as an input in the Risk Management phase that he is currently working in. Which Risk Management phase

Roberto is NOT using a Risk Register as an input in the Risk Management phase that he is currently working in. Which Risk Management phase is Roberto in? Question 5 options: 1) Perform Quantitative Risk Analysis 2) Plan Risk Responses 3) Perform Qualitative Risk Analysis 4) Plan Risk Management