Robin Construction Company began a long term contract in 2021. The contract price was $800,000. The estimated
Fantastic news! We've Found the answer you've been seeking!
Question:
Robin Construction Company began a long term contract in 2021. The contract price was $800,000. The estimated cost of the contract at the time it was begun was $500,000. The actual cost incurred in 2021 was $350,000. The contract was completed in 2022 and the cost incurred was $125,000. Under the percentage of completion method.
a. Robin should report $300,000 of income in 2021.
b. Robin should report $90,000 income in 2022.
c. Robin must pay interest ( under the look-back method) on the underpayment of taxes in 2021.
d. Robin should report $325,000 income in 2021.