Question: Rock n Bands 1 A Project Management Decision - Making Game Around the world or around the block, Everywhere I go , the kids wanna

Rockn Bands1
A Project Management Decision-Making Game
Around the world or around the block,
Everywhere I go, the kids wanna rock2
Your company, Planners 'R Us, specializes in effectively managing projects. Previous
experience has involved conference management systems, commercial construction, and
software development projects.
A new, intriguing project offers another opportunity to apply your project management expertise.
The university you just graduated from wishes to put together a music festival, Rockn Bands.
This will feature a number of top music groups, and should attract interest from students, local
residents, and music fans throughout the region.
Your company has met with University officials to develop a list of activities required to make
Rockn Bands a reality. The list on Page 2 includes twelve activities as well as their durations
and immediate predecessors. The project plan is also described visually on page 2 with a network
diagram. The subscripts on each activity denote the number of weeks of work that activity is
expected to require. Arrows denote the order of activities. For instance, activity E cannot be
started until activity A is completed, and activity H cannot be started until both C and D are
complete. The start and end nodes are dummy nodes and do not need to be worked on. Note that
at the beginning of the project, activities A, C and D are available to start working on, as they
have no predecessor activities. Be sure to understand the diagram before reading further.
Your job is to allocate workers to tasks each week during the project. Planners R Us has agreed
to complete the project in 10 weeks (finishing two weeks before the Festival), and wants to
minimize the costs associated with the project. All tasks A-K must be completed in 10 weeks.
You have four (4) workers, although you do not need to use all of them every week there are
other tasks they can do in your company.
For bookkeeping purposes, your company will charge $200 per week for each worker that you
use. If you happen to need an additional worker, there is one (1) available, but that person would
then not get their other work done; thus, you will be charged $300 per week for the additional
worker. In addition, if the project is late, there will be complications during the last two weeks
before the Festival, costing Planners R Us $2000 per week due to a serious loss of goodwill and
plenty of negative publicity.
The final cost to consider involves expediting tasks. You can assign an extra worker to a task in
any given week in order to finish it in less time. For instance, if a task requires 2 weeks but you
assign two workers, it will be completed in one week. However, putting two workers on a task is
1 The events, activity durations and overall scenario represented in this game are purely fictional. No relationship to
an upcoming music concert, real or implied, is suggested.
2 Bryan Adams, Kids Wanna Rock from the album So Far So Good(1993, A & M Records)
2
not quite as efficient as having one worker complete it from start to finish. Doing this requires
additional coordination (by you) and may require some overtime by the workers. These costs
total an additional $100 per week. The most workers that can be assigned to any task in a week
is two (since having 3 or more requires so much additional coordination that no reduction in time
is achieved). To summarize, the most workers on any given task is two (2) per week, and the
total number of workers you may employ for any week is at most five (5).
Activity Description Duration
(weeks)
Immediate
predecessors
A Contract negotiation with selected music groups 3-
B Find a construction firm & build the stage 5 C
C Contract negotiation with roadies 2-
D Screen and hire security personnel 3-
E Ticket distribution arrangements 1 A
F Organize advertising brochures and souvenir program printing 4 D
G Logistical arrangements for music group transportation 1 E
H Sound equipment arrangements 3 C, D
I Processing of travel visas (for international groups)5 F, H
J Hire parking staff, and make parking arrangements 4 E, B, H
K Distribute media passes and arrange for MTV recording 5 G
L Arrange for concession sales and restroom facilities 2 F
Start
H3
G1
F4
E1
D3
C2
B5
A3
I5
L2
K5
J4
End
Being an experienced manager, you are aware that all projects involve various uncertainties (e.g.,
delays, additional requirements, or even improved efficiency) that can occur at any time. Since
you do not want to lose your reputation for on-time delivery in Planners R Us, you are
determined to plan the project well and be as efficient as possible from the first week on.
For now, you want to develop a plan for the whole project, but the only decision that needs to be
implemented is how to allocate workers for the first week. Report this decision to the instructor

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!